Real Estate News


Section categories

Rent [17]
Land leases [6]
Rental apartments and rooms [27]
Office Rent [22]
City properties [13]
Apartments [54]
New [22]
Residential Real Estate [41]
Bungalow [1]
Summer-houses [14]
Plots [28]
Cottages [23]
International property [73]
Land abroad [1]
Apartments abroad [3]
Islands [8]
Information [86]
Real estate offers [8]
Real Estate News [107]
Property [83]
Commercial Property [23]
Hotels [30]
Residential complexes [2]
Investment Projects [37]
Offices [12]
Estate in Kiev [13]
Estate in Moscow [46]
Properties in Russia [18]
Estate in Ukraine [13]
Other Estate [5]
Non-residential [5]
Miscellaneous [26]
Services [2]
Estate Agents [10]
Mortgage [83]
Exchange, resettlement [9]
Assessment and assistance to lawyers [10]
Apartments for sale [9]
Construction and repair [43]
Transport services [8]
Elite Housing [34]
Locks [4]
Home [34]

Statistics


Total online: 5
Guests: 5
Users: 0

Login form

Publisher

Main » Articles » Real Estate » Construction and repair

What we should finish the house?

- So, the results of the preliminary examination to take into account all the costs dostroyu impossible. In fact, these costs are higher?

- E. NEPOCHATOVA: Unfortunately, it is so. And under the terms of the distribution document, which issued the Moscow Government to address this issue, SU-155 completes its own expense. Compensation of the city is already later. In addition, we are talking about the house, where already sold all the apartments. Thus, finish building the house investor penny from the sale of apartments do not. As for compensation from the city in the amount of funds that the investor spent on dostroy, then this extension of time procedure. All costs must be again confirmed through examination. Sometimes even that is not always possible to prove with documents, these direct costs.

- So why are all the same company taken over dostroy?

- E. NEPOCHATOVA: I will not speak for everyone, but when it comes to our organization, responded to both. We work in this town a long time. We are sorry for the fact that because of such investors, who for various reasons were unable to build their homes, expressed distrust of all other companies. We - one of the largest construction companies, and we are particularly well seen that the whole is suffering from unfinished construction market. Really suffering, because if people do not trust, they do not buy. From this price increases.

- So, you like Chip and Dale, agree to help build, when it requests your company's government? Because a shame for all the construction?

- E. NEPOCHATOVA: Indeed, when we asked the administration, we are not always able to refuse. Nevertheless, all is indeed not so easy, because we are - a commercial organization. Take the example of our finish building on Schelkovo. When the administration asked us to build a house there, we agreed not immediately. The first time we refused, and the administration was negotiating with another firm, with PIK Group. As a result, PIK Group has only two houses. The remaining six homes still returned to us. All the share of housing in these houses, that of 100 thousand square meters. meters sold.

- The situation is understandable: the question of relations with the city. This - and not always profitable commerce. In fact, it is a social burden?

- E. NEPOCHATOVA: Sure.

- And what about the so-called double sales, when the same apartment bought two, and sometimes more than once?

- E. NEPOCHATOVA: Unfortunately, just at the abandoned sites such situations occur. This also applies to costs that can not be taken into account. The list of people who should be granted apartments approved by the Administration. This is logical: the company dostroyschik on a number of good reasons to not have the right to decide what kind of person has the right to claim an apartment, and what not.

- It's not in the zone of your responsibility?

- E. NEPOCHATOVA: Absolutely. Judge for yourself: the investor, say, three years ago, paid only 70% of the apartment. Apartment unfinished. The question is at what price people must pay the remaining 30 percent? According to another contract with a company that went bankrupt, or at today's price? We have no right to make decisions on this issue.

- I do not want?

- E. NEPOCHATOVA: Yes, I do not want. And this is true. That's right, because the decision that the house will be completed, adopted by the Administration. Although in practice we involve employees in the company of people to verify who is seeking apartments in this house, because the administration did not have enough forces, specialists, to check it. Note that this work dostroyschiku nobody pays.

- That is, none at all?

- E. NEPOCHATOVA: Yes. So it has happened.

- By the way, the paper finds mass of letters from indignant readers that, say, the same apartment to various citizens were selling for 4-5 times. What will happen with just such a way cheated by people whom the government refuses to provide apartments?

- E. NEPOCHATOVA: You know, in fact, laws in Russia, no one has repealed. Therefore, the most proper way for everyone - is to go to court. In court - the recognition of the right to claim the apartment.

- But to sue - it is not an easy task?

- E. NEPOCHATOVA: Yes, but at least you will have another court decision, which will have to perform ...

Category: Construction and repair | Added by: Дмитрий (22.03.2010)